Three Braelinn playground designs are quoted at $534,239 to $1.2 million, above the $500,000 planned. A city advisory group discusses them Monday, Nov. 30.

New designs for the Braelinn Recreation Center playground in Peachtree City are priced at $534,239 to nearly $1.2 million. The City Council backed a $500,000 playground there in June.

The three options are in the agenda packet for a special called meeting of the city’s Recreation Advisory Group at 8 a.m. Monday, Nov. 30. The packet holds a quote for each design from GameTime, a playground maker, dated Nov. 23. They come under a single item, “Braelinn Recreation Complex Playground Option Discussion,” in the agenda and packet. The group advises the city and does not spend money itself.

The three options

Every quote includes the equipment, poured rubber surfacing, site work, shade structures, freight and installation. None includes sidewalks, the quotes say.

Option 1 Option 2 Option 3
Play area 9,500 sq. ft. 5,644 sq. ft. 3,895 sq. ft.
Play equipment $689,027.30 $340,271.42 $252,768.83
Installation $263,700.00 $142,875.00 $113,425.00
Discount $284,939.08 $106,794.27 $98,740.93
Grand total $1,198,703.22 $721,717.27 $534,238.87
Bar chart of the GameTime grand totals for the three Braelinn playground options: Option 1 $1,198,703, Option 2 $721,717 and Option 3 $534,239.
The three Braelinn playground quotes, after discounts. Chart by Peachtree City Daily.
Share this chartFacebookWhatsAppX

The quotes say prices are firm for 60 days. The Option 1 drawing in the packet shows a fenced play area beside a ball field, with golf cart play pieces, shaded swings, several slides and a Peachtree City logo set into the surfacing.

How the price climbed

In June, the council wanted to go ahead with a $500,000 playground at the center, 201 Loghouse Road. The city hoped to finish it by spring 2027. In October, the company behind that design stopped honoring its price, the city’s recreation director said. We reported the restart on Nov. 5.

Recreation and Special Events Director Harold Layton then asked for concepts at three price levels: $500,000, $625,000 and $750,000. All three quotes now in the packet come in above those levels. The packet does not say which option the staff prefer.

A roof for the ninja course

The group sent the planned ninja course at the same center to the City Council on Nov. 9. The vote was unanimous, according to the draft minutes of that meeting, which are also in the Nov. 30 packet for approval.

The minutes record these changes to the design:

  • a shade structure over the whole course, which Layton said added $200,000 to the cost
  • a 40-yard dash track with the Peachtree City logo
  • more parking spaces

The course will sit on the other side of the tree line from the tennis courts, the group was told. The minutes do not give the course’s total cost or a council date.

Other parks in the minutes

Layton also updated the group on other projects on Nov. 9, the draft minutes say:

  • Meade playground: the surfacing was due to go in that week.
  • Rockspray and Smokerise: “coming soon” signs are now up at both toddler playgrounds.
  • Battery Way Park: a renovation of about $250,000.
  • Big Pine and Wilder Park: the mayor asked for updates there to be prioritized.
  • Hockey rink: new walls, boards, glass and a water fountain, with a second scoreboard to come and ceiling insulation under study.

Staff keep a working list of park ages. Windalier Ridge, Braelinn and Planterra are at the top, the minutes say. Playground equipment more than five years old cannot be donated, because of liability, the group was told.

The Nov. 30 agenda also has the group choose its member for the steering committee of the city’s 2027 Comprehensive Plan.

What it means for you

  • Braelinn families: the big playground is not settled. The cheapest option on the table costs more than the $500,000 first planned, and no option has been picked.
  • To have a say: the meeting is at 8 a.m. Monday, Nov. 30, in the Recreation Administration conference room, 10 Planterra Way.
  • Ninja course: it goes next to the City Council, which has not yet put it on an agenda.